Staged deployment
State phase-one and ultimate loads separately. Check minimum stable flow and how future racks will be connected.
Assess the TC-CDU-L300C for Australian and New Zealand integration. The catalogue lists 300 kW, 500 L/min and a 600 × 1200 × 2000 mm envelope; confirm the simultaneous duty and installed configuration.
Model datasheet link · no form required · confirm the document revision and quoted configuration.

Assess the initial and final rack loads separately. Its 300 kW and 500 L/min references and 20–100% adjustment range require confirmation at the selected coolant and facility-water conditions; they do not reserve future pipe or electrical capacity.
The L300C reference is 300 kW with 500 L/min and a 600 × 1200 × 2000 mm cabinet envelope. Its listed 20–100% flow adjustment range differs from the 40–100% reference on the L600C. Confirm the actual controlled minimum for your coolant and pump selection.
For an initial Australian or New Zealand POD build, provide both the first-stage rack schedule and ultimate load. Decide whether later expansion uses additional equipment or a replacement cabinet; spare nameplate capacity alone does not reserve pipe or electrical capacity.
Conceptual system boundary only. Connections, flow direction and controls require a project schematic.
State phase-one and ultimate loads separately. Check minimum stable flow and how future racks will be connected.
Agree heat-exchanger approach, primary flow, connection standards and the pressure boundary with the mechanical designer.
Request the controls point list, alarm actions, failover test scope and spare-parts plan for the quoted configuration.
Source: ToneCooling catalogue model data and the linked model datasheet. Listed values are selection references and are not asserted to describe one simultaneous duty point. Confirm coolant properties, inlet/outlet conventions, pressure available to the load, mass basis and offered electrical configuration in the accepted selection.
| Parameter | Catalogue reference |
|---|---|
| Model | TC-CDU-L300C |
| Equipment type | In-Row Liquid-to-Liquid CDU |
| Catalogue capacity | 300 kW |
| Flow reference | 500 L/min |
| Flow adjustment range | 20–100% |
| Head reference — confirm at required flow | 35 m |
| Power consumption reference | < 7.5 kW |
| Catalogue electrical supply | 3-ph AC 380 V 50/60 Hz or 480 V 60 Hz |
| External dimensions | 600 × 1200 × 2000 mm |
| Catalogue mass | 550 kg |
| Pump arrangement | 1+1 |
| Filtration reference | 50 μm |
| Condition | Reference / action |
|---|---|
| FWS temperature reference | 35 °C / 45 °C |
| TCS temperature reference | 40 °C / 50 °C |
| Approach reference | 5 K |
For Australian modular PODs and AI halls, confirm the summer facility-water envelope, installation access and the split between equipment supply and on-site commissioning.
For New Zealand projects, coordinate delivery access, anchorage requirements and the site engineer’s structural review. No seismic qualification is implied by the catalogue.
Model-specific catalogue PDF. Electrical and thermal suitability for your project require written confirmation.
Compare the In-Row Liquid-to-Liquid CDU family · All CDU equipment
ToneCooling Australia Pty Ltd coordinates enquiries for Australian and New Zealand customers. Manufacturing is in Huizhou, Guangdong, China.
Confirm equipment, fittings, coolant, documentation, freight destination and commissioning responsibility. Local stock and on-site service are not implied.
Request the relevant drawings and inspection records. Site approvals, installation and system-level compliance remain separate from a component catalogue description.
Include your company, delivery country and postcode, project stage, prototype quantity and forecast demand. Confirm quotation currency and delivery terms in the commercial offer.
Prepare my enquiry by emailOpens an editable checklist; nothing is sent automatically. Attach drawings before sending. NDA arrangements can be agreed first.
Ask for the selected duty point, pump curve with pressure available to the load, general arrangement, offered electrical configuration, controls point list and acceptance-test scope. Identify document revisions in the quotation.
No. Request a configuration-specific selection using your coolant, air or facility-water conditions and required external pressure. The listed references are not a substitute for an accepted performance curve or test.
Stock, installation, commissioning and response times must be confirmed in the quotation. This page does not promise local inventory or an on-site service network.
No. Confirm the operating conditions, mechanical and electrical interfaces, fluid properties and acceptance test. Catalogue references must match the quoted configuration.
Yes. Include the New Zealand delivery location, site conditions and required documentation so that supply and service responsibilities can be agreed.
Compare model-specific operating conditions, interfaces and supply scope before selection.
CDU circuits and coolant compatibility. ASHRAE TC 9.9 (2019 PDF).
Its liquid-to-liquid examples support the circuit terminology used here. Reference only: no third-party endorsement, certification or verification of ToneCooling catalogue ratings is implied.